POWER
PROJECTS
Fast Track to Darkness
Lopsided privatisation policies have short-circuited
five of the eight showcase power generation schemes.By Shefali Rekhi
Frustrating power cuts, low voltage,
frequent fluctuations. Nothing new, except that the situation may well get worse this
year. The government did promise many more power plants. But flawed thinking and
bureaucracy has short-circuited those intentions. Of the eight fast-track projects
selected in 1992 -- and to be completed by '96 -- only two are now generating power. A
third, Enron's Dabhol, will get commissioned by this December. The rest haven't even
started civil work yet.
The three projects that are on will add to the country's
power capacity by just one-fifth of what was originally intended. A basic flaw in the
privatisation policy delayed the projects. Private entrepreneurs will not bite till they
are certain about profits. In this case, the power producers had to sell the power to the
state electricity boards (SEBs), but 18 of the 19 SEBs are in the red with total losses in
excess of Rs 10,000 crore. The SEBs made losses because they were not allowed to charge a
reasonable rate for power sold to consumers -- in fact, in some states like and Punjab,
power is given free to farmers. The states did promise to compensate for the losses, but
it was never adequate. Finally, the Centre came forward to announce counter-guarantees.
But these counter-guarantees fall flat against future
risks. Two years after the government made its promise, international prices of power
project equipment plummeted by a sharp 20 per cent. It was something even the private
players did not anticipate. But it led to a new debate about whether the projects were
heavily padded on the cost front. In Orissa, the state Government prevailed upon the
promoters of the IB Valley project to submit a new bid, with the revised rates. At one
point there was even talk of cancelling the Enron project in Maharashtra for which
guarantees had been extended.
Overnight, the Ministry of Finance (MOF) turned cautious,
asserting that it would independently examine power purchase agreements (PPAs) negotiated
between the producers and the SEBs. Till date, PPAs have not been cleared for the
remaining five projects. Many other issues have cropped up alongside to cripple progress.
And the way things are at the moment, it's going to be a really hot summer ahead. New
Minister for Power Rangarajan Kumaramangalam has promised radical reforms, but it's easier
said than done. Here's a report on where the five projects are stuck:
Orissa:IB VALLEY THERMAL POWER PROJECT
Capacity: 420 MW, now hiked to 500 MW
Cost: Rs 1,993 crore (for 420 MW)
Promoters: AES Transpower of USA
MoU: December 9, 1992
IB Valley was the first company to sign the PPA as early as
in 1993 and was to begin construction soon after. But when international prices of power
project equipment fell in 1995, the Orissa Government prevailed upon the promoters to
rebid. In the proces, the company slashed its capital cost by 20 per cent, on a cost per
MW basis, but at the same time managed to push for higher capacity from 420 MW to 500 MW
for economies of scale.This meant going through the red tape all over again.
The revised report was submitted in August 1997 but IB
Valley is yet to get the techno-economic clearance from the CEA. Hamsa Shadakasharappa,
director, AES India, believes: "Everyone underestimated the complexities of
privatising the power sector."
The CEA certified the project in July 1996. But its PPA has
run into a technical snag. According to a cabinet decision of 1994, SEBs going in for such
agreements should have a rate of return of 3 per cent. But here it is a negative 14 per
cent. Chief Minister N. Chandrababu Naidu has requested for a waiver, which the Union
Cabinet has to consider. Fuel supply is also a problem. The company has to transport its
coal over 600 km from Mahanadi coalfields, for which it has to sign an agreement.
Precedents do not exist and both parties are worried about the risks involved. "There
are guidelines," points out A. Gavisidappa, managing director, "but there is a
problem about the interpretation of the written word." Till then, pockets in Andhra
Pradesh will continue to suffer power cuts.
Andhra Pradesh: VISHAKHAPATNAM THERMAL POWER PROJECT
Capacity: 1,000 MW
Cost: Rs 4,253 crore
Promoters: Cogentrix Inc, USA and China Light and Power International
MoU: July 30, 1992
Apart from a review of the PPA and the tariff schedules by
different wings of the Government, there is another technical issue that is affecting
progress. A transmission system to absorb the power that will be produced by this project
does not exist. The state Government wants to set this up through a joint-sector company
for which it has lined up a private producer who has no stake in the generation project.
As per law, only private producers with a stake in generation can be permitted to
participate in a transmission joint venture. The Karnataka Government has sought an
exemption from the Centre and an ordinance to be issued for amending the relevant
provision in the Electricity Supply Act. The project is also grounded because of the court
cases against it, involving damage to the environment and allegations that bribes were
paid to state officials. At one stage, the Karnataka High Court even directed the CBI to
file a criminal case. But this has now been stayed by the Supreme Court.
Karnataka: MANAGALORE THERMAL POWER PROJECT
Capacity: 250 MW
Cost: Rs 1,325 crore
Promoters: ST-CMS Electric Company, USA
MoU: August 8, 1992
In the '80s, the public sector Neyveli Lignite Corporation
(NLC) was operating a power unit with a capacity of 2070 MW based on the lignite mined in
the area. It proposed to set up a 210 MW plant to utilise the surplus lignite. The project
was appraised by the CEA and given a techno-economic clearance in August 1988. But owing
to a resource crunch, NLC was unable to pursue the project.
With the advent of privatisation, the government decided to
hand it to the private sector and an MoU was signed with the new promoters. The project
size was subsequently increased to the internationally accepted 250 MW. This meant
clearances all over again. The PPA and the tariff schedule are being examined by the
ministries of power and finance. The deadline set for the signing of a fuel supply
agreement with the Ministry of Coal was January 28 this year, but the document is still
not in place. The way things stand now, the government's counter-guarantee is still a long
way off.
Tamil Nadu: NEYVELI THERMAL POWER PROJECT
Capacity: 1,082 MW
Cost: Rs 5,187 crore
Promoters: Ispat Group with GEC of UK and EDF of France
MoU: June 18, 1993
The difference between Bhadravati and the other projects is
that the company wants its own captive coal-mining unit. But this is also the root cause
of all its troubles as it has had to float a new company for the captive unit. The logic
behind this was that the promoters for the captive unit were different from the ones for
the generating plant. But this has got the bureaucracy all knotted up as it wants to know
whether the new company can technically qualify to be called a captive power unit. And
would guidelines be violated if it got the privileges given to captive units.
There are other objections too. The new captive unit will
produce coal in excess of demand, which the SEB has agreed to buy. But government
officials are trying to ensure that it will violate no law, policy or guideline by doing
so. There is also the problem of location close to an ordinance factory. The Ministry of
Defence's response is still awaited. Meanwhile, a petition is pending against the company
on the issue of location and the Nagpur High Court has stayed land acquisition for the
coal mine till the Department of Defence Production takes a final view on the issue. |